Pre-Launch Updates
Nov 05, 2013
- PSLV-C25, in its twenty fifth flight successfully launches Mars Orbiter Mission Spacecraft from SDSC SHAR.
- PSLV-C25 lifted off at 14:38 hrs.
- Automatic sequencing of launch initiated.
- Launch authorised by Mission Director for GO at 14:24 hrs.
- Mobile Service Tower (MST) withdrawal to final parking (150m) completed. Countdown is normal.
- All vehicle systems are switched ON for the final eight and half hour countdown starting at 6:08 hrs (IST).
- Second Stage (PS2) Propellant filling operations completed.
Nov 04, 2013
- Second Stage (PS2) Propellant filling commenced.
- Mobile Service Tower (MST) withdrawal upto 50m is completed.
- Mandatory Checks and Preparations for Propellant filling operations of Second Stage (PS2) are in progress.
Nov 03, 2013
- Propellant filling of PS4 stage and RCT completed.
- Mixed Oxides of Nitrogen (MON) filling of PS4 completed at 17:00 hrs (IST).
- Mixed Oxides of Nitrogen (MON) filling of PS4 under progress.
- Mono Methyl Hydrazine (MMH) filling of Reaction Control Thrusters (RCT) completed.
- Mono Methyl Hydrazine (MMH) filling completed.
- Propellant filling operations of Fourth Stage (PS4) are in progress.
- The 56 hr 30 min countdown of Mission commenced at 06:08 hrs (IST).
Nov 02, 2013
- All the pre-countdown activities have been completed satisfactorily and the 56 and half hr countdown of Mission will commence tomorrow at 06:08 hrs (IST).
- Pre-count down activities of Mission commenced at 08:45 hrs.
Nov 01, 2013
- Launch Authorisation Board has approved & cleared the PSLV-C25/Mars Orbiter Mission launch on Nov 05, 2013 at 14:38 hrs (IST)
- 56 and half hr countdown for launch will begin on Nov 03, 2013 at 06:08 hrs (IST)
Oct 31, 2013
- Launch Rehearsal of PSLV-C25/Mars Orbiter Mission has been completed successfully in the afternoon on Oct 31, 2013.
- Launch Rehearsal of PSLV-C25/Mars Orbiter Mission commenced at 06:08 hrs (IST) on Oct 31, 2013 at First Launch Pad, SDSC SHAR.
- Vehicle systems powered and health is normal.
Oct 30, 2013
- Spacecraft & Launch Vehicle integrated level checks completed.
- Preparations for Launch Rehearsal are under progress.
Oct 22, 2013
- Spacecraft Integration with the Launcher PSLV-C25 Completed.
- Heat Shield Closure Activity is completed.
|
|