Thursday, 9 January 2014

Pre-Launch Updates

Nov 05, 2013
  • PSLV-C25, in its twenty fifth flight successfully launches Mars Orbiter Mission Spacecraft from SDSC SHAR.
  • PSLV-C25 lifted off at 14:38 hrs.
  • Automatic sequencing of launch initiated.
  • Launch authorised by Mission Director for GO at 14:24 hrs.
  • Mobile Service Tower (MST) withdrawal to final parking (150m) completed. Countdown is normal.
  • All vehicle systems are switched ON for the final eight and half hour countdown starting at 6:08 hrs (IST).
  • Second Stage (PS2) Propellant filling operations completed.
Nov 04, 2013
  • Second Stage (PS2) Propellant filling commenced.
  • Mobile Service Tower (MST) withdrawal upto 50m is completed.
  • Mandatory Checks and Preparations for Propellant filling operations of Second Stage (PS2) are in progress.
Nov 03, 2013
  • Propellant filling of PS4 stage and RCT completed.
  • Mixed Oxides of Nitrogen (MON) filling of PS4 completed at 17:00 hrs (IST).
  • Mixed Oxides of Nitrogen (MON) filling of PS4 under progress.
  • Mono Methyl Hydrazine (MMH) filling of Reaction Control Thrusters (RCT) completed.
  • Mono Methyl Hydrazine (MMH) filling completed.
  • Propellant filling operations of Fourth Stage (PS4) are in progress.
  • The 56 hr 30 min countdown of Mission commenced at 06:08 hrs (IST).
Nov 02, 2013
  • All the pre-countdown activities have been completed satisfactorily and the 56 and half hr countdown of Mission will commence tomorrow at 06:08 hrs (IST).
  • Pre-count down activities of Mission commenced at 08:45 hrs.
Nov 01, 2013
  • Launch Authorisation Board has approved & cleared the PSLV-C25/Mars Orbiter Mission launch on Nov 05, 2013 at 14:38 hrs (IST)
  • 56 and half hr countdown for launch will begin on Nov 03, 2013 at 06:08 hrs (IST)
Oct 31, 2013
  • Launch Rehearsal of PSLV-C25/Mars Orbiter Mission has been completed successfully in the afternoon on Oct 31, 2013.
  • Launch Rehearsal of PSLV-C25/Mars Orbiter Mission commenced at 06:08 hrs (IST) on Oct 31, 2013 at First Launch Pad, SDSC SHAR.
  • Vehicle systems powered and health is normal.
Oct 30, 2013
  • Spacecraft & Launch Vehicle integrated level checks completed.
  • Preparations for Launch Rehearsal are under progress.
Oct 22, 2013
  • Spacecraft Integration with the Launcher PSLV-C25 Completed.
  • Heat Shield Closure Activity is completed.